What are the procedures for a topographic (TOPO) survey review?

A topographic design must be submitted when building a new home.  This TOPO must be stamped by a licensed surveyor and should show the building structure, and the existing and proposed contours and spot elevations of the property.  Four copies of the TOPO are needed for the Engineering Department’s review.

Once approved the TOPO is then sent to the Building Department to be given back to the contractor with the building permits.